Location |
The station has been built in Belgium – Oostrozebeke – Ingelmunstersteenweg (next to the chipboard plant “Spano”) for A&S ENERGIE NV |
| Operator |
A&S ENERGIE NV |
|
| Planning and construction |
N.prior energy as general contractor |
|
| Date of commissioning |
Mid-2010 |
|
| Total investment |
approx. 65 million € |
|
| Technology |
Circulating fluid bed boiler |
|
| Fuels |
Approx. 180,000 tons per year of wood waste AI-AIV, flotsam, renewable raw materials and other biomass as defined by the German Biomass Ordinance concerning the Renewable Energy Act (EEG), approx. 180,000 tons p.a. |
|
| Performance data |
The power station produces 25.2 MWel throughout the year and has a thermal output of 75 MW. Steam parameters: 500 °C and 89 bars. |
|
| Energy yield |
The electric capacity is approx. 200 gigawatt hours p.a. |
|
| Special Features |
Option: The boiler has been designed and prepared for serving as a thermo-oil-heat-exchanger (5.8 MW thermal) for the process heat of the chipboard factory. |
|
News
Effiziente und ökologische Energieerzeugung: Biomasseheizkraftwerke punkten nachhaltig
There are no translations available.
Leer, 17. Januar 2011 – Mittlerweile zeichnet sich ab, dass ohne Energie aus Biomasse die angestrebten Klimaschutzziele nicht erreichbar sind. Umso wichtiger ist es, diese Form der Energieerzeugung regional und
international auszubauen.