8 Tacke 1.5s
Hub height: 85 m
Date of commissioning: 1999
Average annual wind speed: 6.4 m/s
Annual energy yield: 22.4 million kWh
News
Effiziente und ökologische Energieerzeugung: Biomasseheizkraftwerke punkten nachhaltig
Leer, 17. Januar 2011 – Mittlerweile zeichnet sich ab, dass ohne Energie aus Biomasse die angestrebten Klimaschutzziele nicht erreichbar sind. Umso wichtiger ist es, diese Form der Energieerzeugung regional und
international auszubauen.
Onshore Wind Energy
Since 1997, we have been established in the onshore market as planning and operating company of totally 13 wind farms and two testing areas: with an installed capacity of 138 MW (42 MW of which are owned by N.prior energy), the wind farms initiated by us produce 280 million kilowatt hours per year. This means a supply of 90,000 households. The resulting revenues ensure a steady and calculable company cash flow. In the onshore sector, we regard our expertise in the „Repowering“ segment for the future. Our company replaces old wind energy converters by newer and more efficient ones to increase the energy yield.
Wind farm Quenstedt (Saxony-Anhalt)
Wind farm Bütow/Zepkow (Mecklenburg-West Pomerania)
22 DeWind 48
Hub height:Nabenhöhe 70 m
Date of commissioning: 1999
Average annual wind speed: 5.9 m/s
Annual energy yield: 24.1 million kWh
Wind farm Klostermoor (Lower Saxony)
8 Enercon E66
Hub height: 66m
Date of commissioning: 1998 / 1999
Average annual wind speed: 6.8 m/s
Annual energy yield: 23.7 million kWh
Wind farm Weenermoor (Lower Saxony)
12 Enercon E66
Hub height: 66 m
Date of commissioning: 1998 / 1999
Average annual wind speed: 7 m/s
Annual energy yield: 37.5 million kWh